GCP Cost and Billing Basics
Query billing export, skim the Architecture Framework's pillars, and compare On-Demand, Committed Use, and Spot pricing for one machine type, math shown.
By SkillByExample · Published
Cost control on GCP is less about any one setting and more about knowing where to look: billing export for what was actually spent, budgets for getting warned before it goes further, and pricing model choice for what a workload should cost in the first place. This lesson walks all three, ending with real numbers for one machine type.
Billing export to BigQuery
Detailed billing data isn’t queryable through gcloud directly — it has to be exported to
BigQuery first.
gcloud billing accounts get-iam-policy 01A2B3-4C5D6E-7F8A9B --format=none # confirms access
bq query --use_legacy_sql=false '
SELECT
service.description AS service,
ROUND(SUM(cost), 2) AS total_cost
FROM `skillbyexample-437219.billing_export.gcp_billing_export_v1_01A2B3_4C5D6E_7F8A9B`
WHERE DATE(usage_start_time) >= DATE_SUB(CURRENT_DATE(), INTERVAL 30 DAY)
GROUP BY service
ORDER BY total_cost DESC
'
+--------------------------+------------+
| service | total_cost |
+--------------------------+------------+
| Compute Engine | 84.32 |
| Cloud SQL | 41.60 |
| Cloud Storage | 6.14 |
| Cloud Run | 0.87 |
+--------------------------+------------+
This is the actual granular source of truth for spend — the Console’s billing overview page summarizes the same underlying export table.
Setting a budget alert
gcloud billing budgets create \
--billing-account=01A2B3-4C5D6E-7F8A9B \
--display-name="Monthly project cap" \
--budget-amount=150.00 \
--threshold-rule=percent=0.5 \
--threshold-rule=percent=0.9 \
--threshold-rule=percent=1.0
Created budget [billingAccounts/01A2B3-4C5D6E-7F8A9B/budgets/a1b2c3d4-e5f6-7890].
Three thresholds fire three separate notifications — at 50%, 90%, and 100% of $150 — to the billing account’s administrators by default. A budget alert never stops a resource from running; it’s purely a notification.
The Architecture Framework’s cost pillar, at a glance
Google’s Architecture Framework reviews a design against five pillars, with sustainability applied as a cross-cutting concern over all of them:
Pillar What it asks
---------------------------------------------------------------------------
Operational excellence Can you deploy, monitor, and run this reliably?
Security, privacy, compliance Is data and access appropriately protected?
Reliability Does it meet its availability target under failure?
Cost optimization Is spend proportional to the value delivered?
Performance optimization Does it meet latency/throughput needs efficiently?
Cost optimization specifically isn’t “spend the least” — it’s matching commitment level and machine shape to actual, measured usage, which is exactly what the next section quantifies.
On-Demand vs Committed Use vs Spot, for one machine type
Comparing n2-standard-4 (4 vCPU, 16 GB memory) in us-central1, published list prices at
time of writing:
Pricing model $/hour Discount vs On-Demand
---------------------------------------------------------
On-Demand 0.1942 —
1-year Committed Use 0.1223 37%
3-year Committed Use 0.0874 55%
Spot 0.0463 76%
Extending to a full month (730 hours, the standard GCP billing convention for “a month”):
On-Demand: 0.1942 * 730 = $141.77 / month
1-year Committed Use: 0.1223 * 730 = $89.28 / month (save $52.49, 37.0%)
3-year Committed Use: 0.0874 * 730 = $63.80 / month (save $77.97, 55.0%)
Spot: 0.0463 * 730 = $33.80 / month (save $107.97, 76.2%)
The catch scales with the discount. A 1-year CUD bills $89.28 every month for 12 months regardless of whether the VM runs the full month or sits idle — committing a workload that actually only runs half the month would make the “discount” cost more than On-Demand billed for actual usage ($70.89). Spot is the cheapest by far, but Google can reclaim a Spot instance with 30 seconds’ notice, which rules it out for anything that isn’t fault-tolerant and checkpointable.
Choose On-Demand for short-lived or unpredictable workloads
Choose Committed Use for a proven, steady-state baseline you'll run 12-36 months regardless
Choose Spot for fault-tolerant batch jobs that can restart cleanly
Practice
1. Calculate the break-even utilization for the 1-year CUD versus paying On-Demand only while running.
CUD monthly cost: $89.28 (fixed, regardless of usage)
On-Demand cost per hour of actual use: $0.1942
Break-even hours: 89.28 / 0.1942 = 459.7 hours
459.7 / 730 = 63.0% utilization
Below 63% utilization in a month, paying On-Demand only for the hours actually used is cheaper than committing to the 1-year discount — the CUD only pays off past that line.
2. Query billing export for cost broken down by label instead of by service.
bq query --use_legacy_sql=false '
SELECT
(SELECT value FROM UNNEST(labels) WHERE key = "env") AS environment,
ROUND(SUM(cost), 2) AS total_cost
FROM `skillbyexample-437219.billing_export.gcp_billing_export_v1_01A2B3_4C5D6E_7F8A9B`
WHERE DATE(usage_start_time) >= DATE_SUB(CURRENT_DATE(), INTERVAL 30 DAY)
GROUP BY environment
'
+-------------+------------+
| environment | total_cost |
+-------------+------------+
| production | 102.44 |
| staging | 21.90 |
| NULL | 7.99 |
+-------------+------------+
The NULL row is resources with no env label at all — a common finding the first time
anyone runs this query, and usually the argument for a label-enforcement policy.
3. List existing budgets and check which one is closest to its threshold.
gcloud billing budgets list --billing-account=01A2B3-4C5D6E-7F8A9B \
--format="table(displayName,amount.specifiedAmount.units)"
DISPLAY_NAME UNITS
Monthly project cap 150
gcloud reports the budget’s configuration, not live spend against it — actual percent-consumed
requires the billing export query from the first example, filtered to the current month.
4. Recompute the comparison table for e2-standard-4 instead of n2-standard-4, using its lower on-demand rate of $0.1611/hour and the same discount percentages.
On-Demand: 0.1611 * 730 = $117.60 / month
1-year Committed Use: 0.1015 * 730 = $74.10 / month
3-year Committed Use: 0.0725 * 730 = $52.93 / month
Spot: 0.0384 * 730 = $28.03 / month
The percentage savings carry over almost exactly across machine families because CUD and Spot discounts are applied as a rate off whatever the on-demand price is, not a flat dollar amount.
5. Delete the budget created earlier.
gcloud billing budgets delete billingAccounts/01A2B3-4C5D6E-7F8A9B/budgets/a1b2c3d4-e5f6-7890 --quiet
Deleted budget [billingAccounts/01A2B3-4C5D6E-7F8A9B/budgets/a1b2c3d4-e5f6-7890].
Deleting a budget only removes the alert — it has no effect on any resource or on spend that already happened.
This closes the GCP track. Between the free-tier credit from the first lesson and Spot pricing from this one, every example here can be rerun for well under a dollar.